In short: Whether a society can start redevelopment without conveyance depends on its title and on what the developer and the authorities require. Most societies complete conveyance or deemed conveyance before inviting offers from developers, because until then the land records still show the builder or landowner as owner.
Why the question arises
Redevelopment means demolishing the building and constructing a new one on the same land. The person who does that needs the right to deal with the land. Until the builder conveys the land and building to the society under section 11 of the Maharashtra Ownership Flats Act, 1963 (MOFA), the property card or 7/12 extract continues to show the builder or the landowner as owner.
A society without conveyance is therefore asking a developer to build on land that, on record, still belongs to someone else.
The section 79A directions
The redevelopment of a co-operative housing society's building follows the directions issued by the State Government under section 79A of the Maharashtra Co-operative Societies Act, 1960. They deal with how the society holds its meetings, appoints its consultants, invites offers and selects a developer. The directions have been revised from time to time, so a committee should check the Government Resolution currently in force before it starts. See the redevelopment checklist.
Where the absence of conveyance causes difficulty
- The development agreement. The society signs as owner. Without conveyance, the builder or landowner may have to join the agreement or give consent, which is often the very thing that could not be obtained earlier.
- Finance. A developer raising project finance, or a society raising funds for self-redevelopment, is asked for clear title to the land.
- Unused development potential. Who is entitled to the unused FSI of the plot is settled far more easily once the land stands in the society's name.
When societies proceed without it
Some societies begin the redevelopment process while a deemed conveyance application is pending, so that the two run together. Others proceed where the builder or landowner is willing to sign the development agreement as a confirming party. Both carry more risk than completing the conveyance first, because the society's rights depend on an application not yet decided or on another party's continued co-operation.
The usual order of work
- Collect the society's registration certificate, the members' registered agreements with index II, the property card or 7/12 extract, the city survey plan and the approved plans.
- Call on the builder and landowner to execute a conveyance.
- If they do not, apply for deemed conveyance under section 11(3) of MOFA.
- Register the deed and have the land records changed to the society's name.
- Then begin the redevelopment process under the section 79A directions.
Section 11(4) of MOFA requires the competent authority to decide within a reasonable time and in any case within six months. Stamping, registration and the change in the land records follow after that.
The Government Resolution of 22 June 2018 sets out four stages: the order and certificate, adjudication of stamp duty, registration, and entry of the society's name in the land records. It treats the procedure as complete only after the last. A committee planning redevelopment should allow time for all four, not only for the order. The step-by-step guide sets them out.
For a committee deciding what to do first
- Check what the property card or 7/12 extract shows today.
- Find out whether the builder and landowner exist, can be traced and are willing to sign.
- Ask each developer who makes an offer how it proposes to deal with title, and compare the answers.
- Record the decision in a general body resolution, so that members know why the society chose the order it did.
Common questions
Can a society sign a development agreement without conveyance?
It may be possible, depending on the title and the parties' authority. If the society does not hold title, the agreement may need to include the landowner or other titleholder, or rely on their valid authorisation. The society cannot grant development rights it does not hold. Without conveyance, establishing the society's authority and obtaining approvals is harder, and conveyance or deemed conveyance gives the society a stronger footing. The Co-operation Department's online deemed conveyance page calls the non-availability of conveyance a major hurdle to redevelopment.
Can a society apply for deemed conveyance and start redevelopment together?
The two can run in parallel, but the society's ability to make binding redevelopment arrangements depends on its title and authority. If conveyance is pending, the landowner or other titleholder may need to join or authorise the agreement. Completing conveyance first generally gives the society a clearer basis for redevelopment.
How long does deemed conveyance take?
Section 11(4) of MOFA requires the competent authority to decide the application within a reasonable time and in any case not later than six months of receiving it (MOFA, section 11(4)). That period covers the authority's decision; stamping, registration and mutation follow. The Government Resolution of 22 June 2018 asks the Sub-Registrar to complete registration within one day once the required steps and documents are in place, and mutation follows the land-record procedure.
This article is general information about the law in Maharashtra as of November 2026. It is not legal advice, and the right course in any case depends on its facts.